Town of Gibsonville-USDA Sanitary Sewer Rehabilitation Project

Smoke Image.webAWCK is working with the Town of Gibsonville to assist the Town in both identifying and removing sources of inflow and infiltration into the sanitary sewer system. The project began with a downtown inflow and infiltration study which led to identification of several large inflow points. The original study is the basis for the current Engineering Report and Environmental Information Document that will inform an application to USDA for funding assistance. The estimated complete project cost is $2.25 million.

 

Project Contact: Mr. Ben Baxley, Town Manager (336)449-4144
Project Manager: Josh Johnson, PE
Project Engineer: Troy King, PE
Estimated Cost: $2,250,000
Completion: Spring 2016.

Gibsonville Sewer Map - Smoke Testing.web